The Amperage Atlas - Capitol & Capacity · Indiana · No. 13 of 26Research

Indiana: The Quiet State That Wrote the Rules First

While its neighbors froze and litigated, Indiana passed a large-load tariff, landed Meta's gigawatt campus, and became the Midwest's default yes, with one NDA scandal showing the cost

Indiana's Atlas profile is the inverse of its neighbors': maximal buildout, minimal drama. Meta's Lebanon campus, internally Project Domino, broke ground in February 2026 at the LEAP district in Boone County, a $10 billion-plus, 1 GW program across roughly 1,500 acres and 4 million square feet in up to 15 buildings. A pipeline of 56 projects makes Indiana a top-tier Midwest destination, and EPRI projects data centers exceeding 20 percent of state electricity demand, among the highest shares in America. Indiana got there by doing early and quietly what other states are now doing late and loudly.

FULL ANALYSIS  •  FACTUAL, CITED  •  JULY 2026

Capitol: The First-Mover Tariff

Indiana's signature policy is a February 2025 commission order that predates most of the national debate: data centers and other large loads must give utilities five years' advance notice before reducing electricity demand by more than 20 percent, with plans submitted for state review. The order attacks the stranded-asset problem at its root; if a hyperscaler walks, Indiana ratepayers are not left holding generation built for a ghost. Combined with the state's long-standing sales tax exemption (every Midwestern state except Nebraska and South Dakota offers data center incentives, and Indiana's is among the most durable), the package gives developers what they price above all else: rules that exist, in writing, before groundbreaking. The 2026 session added guardrail proposals in the S.B. docket, but Indiana's legislature has so far declined the freeze-and-fight path of Illinois or Michigan, and the governor's office remains promotional.

Capitol: Posey County and the Price of Quiet

The transparency bill is coming due in one corner of the state. Posey County officials confirmed signing a non-disclosure agreement with a data center developer, triggering public calls for a temporary moratorium and greater disclosure, and turning a routine siting into the state's test case on secrecy. The pattern is national, NDAs are standard site-selection practice everywhere, but Indiana's permissiveness makes it the state where the practice faces the least countervailing process, and therefore where a backlash, when it lands, lands hardest. The Wisconsin record, where discovered emails converted a permitting dispute into statewide litigation, is the cautionary precedent Indiana's county councils are now reading.

Capacity: LEAP, Lebanon, and the Battery Corridor

The LEAP Research and Innovation District, 30 miles northwest of Indianapolis, is the physical expression of Indiana's strategy: a state-assembled megasite with water and power pre-planned, into which Meta is building one of its largest campuses with advanced closed-loop liquid cooling designed to minimize water draw, roughly 4,000 trade workers at peak and about 300 operational roles. Around it, the manufacturing layer thickens: GM and Samsung SDI's 30 GWh battery cell plant at New Carlisle anchors the state's storage supply chain, and Indiana's legacy grid, AEP, Duke, and NIPSCO territory inside MISO and PJM's seam, gives developers a choice of markets few states can offer. The 20-percent-of-load projection is the flip side: Indiana is absorbing demand at a share that will test every assumption in its utilities' integrated resource plans, and the state's coal-heavy generation base makes the emissions trajectory of that growth a coming federal and corporate-procurement issue.

Signals: What the Distress Monitor Shows

Indiana's gauges read steady with three flags. Concentration of new load in a coal-tilted MISO/PJM seam invites both reliability scrutiny and clean-energy procurement friction as hyperscaler PPAs chase scarce regional renewables. The Posey County episode is small but directional; a single ballot measure or council flip in a key county would be the first crack in the default-yes model. And the neighbor effect cuts both ways: Illinois's freeze and Michigan's moratorium bills are actively routing projects to Indiana today, but they are also routing the politics, and the activist networks organizing in Chicago and Ann Arbor work across state lines. The counterweights are the strongest in the region: rules that pre-date the backlash, a delivered megasite model in LEAP, and a tariff that already answers the stranded-cost question every other legislature is still debating.

Atlas Rating: Balanced

Indiana rates Balanced, the Midwest's only such grade: demand and supply are growing together under rules set in advance, with the five-year notice tariff standing as the Atlas's best example of pre-emptive policy. The bull case is that Indiana becomes the Midwest's Texas, the jurisdiction where certainty compounds into durable market share while neighbors litigate. The bear case is that quiet was purchased with opacity, and that a 20-percent load share arriving on a coal-heavy grid, negotiated under NDAs, eventually produces the backlash all at once rather than in installments. For now, Indiana is what the industry says it wants everywhere else, and the Atlas will watch whether wanting it built survives getting it.

Sources

1. Blackridge Research / Meta, Lebanon campus (Project Domino): $10 billion-plus, ~1,500 acres, 4 million sq ft, February 2026 construction start, closed-loop cooling; workforce figures, June 2026.

2. CSG Midwest, February 2025 five-year advance-notice tariff order; EPRI 20 percent-plus load projection; Midwest incentive landscape, May 2026.

3. Data Centers Daily Notes, Posey County NDA confirmation and moratorium calls, July 22, 2026.

4. datacenter.fyi, Indiana pipeline (~56 projects), 2026.

5. Charged EV supply chain map, GM/Samsung SDI New Carlisle 30 GWh, 2023-2026.

6. Newsweek, Indiana 2026 legislative proposals, May 2026.